Nampa Interstate 84 interchange work starts next month

By Cynthia Sewell - csewell@idahostatesman.com

Published: 11/04/09


Bookmark and Share
Share on Twitter Share on Facebook
print story email story to a friend
Comments (0) |

Concrete Placing Co. Inc. of Boise is the apparent low bidder on Interstate 84 improvements for the Garrity Boulevard interchange bridge and from 11th Avenue to Garrity, according to the Idaho Transportation Department.

Construction is expected to last about 18 months, beginning in December and finishing in June 2011.

Bids on the project were opened Tuesday. The low bid of $14.9 million was one of six bids received.

The project will remove two bridges at the Garrity interchange in Nampa and replace them with a single bridge to accommodate three lanes in each direction on I-84. Work also includes reconstructing the interstate about a mile east of the interchange to tie into the Garrity interchange to Meridian interchange widening project currently under way on the interstate.

OPTIONS: Most Read Stories  |  Story Comments  |  Email story  |  Print story
hide comments

Story Comments
We welcome comments but ask that you remain on topic. Some comments may be reprinted elsewhere in the site or in the newspaper. Comments that are profane, personal attacks or otherwise inappropriate or are off topic are subject to removal. Repeat offenders will be blocked. Do not flag comments merely because you disagree with the comment.

more about comments here.
Local Deals
Find a Job
Keywords:
Location: